1. Activity Based Costing
... doing it on their own. The following is the total time needed for each activity in building the wall. Activity Contractor (duration in hours) Done by owner (duration in hours) Design Wall 4 10 Prepare Site 8 8 Lay foundation 2 2 Build Wall 7 11 Backfill Wall 3 3 Total 24 34 Depending on the duration, the decision might be to let the contractor perform the job as ... about the amount charged for each activity. The materials will still cost the same amount for the contractor or the owner. Hourly rates for work [7]. Personal Time $ 40 per hour Design by contractor $150 per hour Hand Labor ...